← All Case Studies
⚠️ Section 301 Tariff Escape

Outdoor Power Equipment Steel Chassis

Stamping & welded assembly — 42% landed cost savings, Section 301 tariffs eliminated

Stamping MIG Welding Powder Coating China+1
42%
Landed Cost Savings
$0
Section 301 Tariff
8 wk
To First Samples
est. $480K
Annual Savings
🚨

Section 301 Tariff Impact — Before Migration

This client was paying 25% Section 301 tariffs on Chinese-origin steel fabrications (HTS Chapter 73). On $1.1M annual import value, that was $275,000/year in pure tariff cost — on top of an already uncompetitive unit price. Vietnam is not subject to Section 301 tariffs.

The Challenge

A U.S. manufacturer of commercial outdoor power equipment was sourcing welded steel chassis assemblies from a single factory in Guangdong, China. The chassis — a complex multi-part weldment in 2.5mm and 3mm SPCC steel — was subject to 25% Section 301 tariffs under HTS Chapter 73. Their landed cost per unit had climbed to $218, up from $165 three years prior, entirely due to tariff escalation.

Annual volume was approximately 5,500 units. The procurement team needed to qualify a new supply source fast — ideally before the next tariff escalation cycle — without disrupting their existing production schedule or accepting quality regression.

Why Vietnam?

$0
Section 301 tariff on Vietnam-origin steel fabrications
16+
Free Trade Agreements — CPTPP, RCEP, bilateral FTAs
179+
Dewin-audited factories including stamping & welding specialists

Vietnam's steel fabrication sector has expanded significantly, with many factories running Trumpf laser cutters, progressive-die stamping presses up to 1,000 tonnes, and robotic MIG welding cells. Our network includes over 30 factories specializing in sheet metal stamping and structural welded assemblies — all with Dolphin audit scores on file.

1. Drawing Package Review & Process Breakdown

The chassis assembly comprised 11 individual stamped components welded into a single structural frame, plus powder coat finish and hardware assembly. Our Vietnam engineering team reviewed the full drawing package and flagged the key process requirements:

  • Material: SPCC/SPHC steel, 2.5mm and 3.0mm gauge — widely available in Vietnam from POSCO and local steel distributors
  • Stamping: Blanking, forming, and piercing — 7 progressive-die parts, 4 single-hit parts
  • Welding: MIG, 18 weld joints, including 4 structural fillet welds with AWS D1.1 requirements
  • Finish: Epoxy powder coat, RAL 7016 anthracite grey, 60–80 μm DFT
  • Assembly: 6 fastener locations, M8 & M10 inserts, final dimensional check to ±1.0 mm overall

We identified two factories in our audited network capable of handling the full scope in-house — stamping, welding, and powder coat — to minimize handoffs and freight between sub-suppliers.

2. Factory Audit & Qualification

Our on-ground team conducted Dolphin audits at both shortlisted facilities within two weeks of project kick-off. Audit scope included:

  • Press room: Aida 800T and 630T progressive die presses with servo control — ideal for the 3mm SPCC forming requirements
  • Welding area: 8 Lincoln Electric robotic MIG cells + manual backup stations; certified welders to AWS D1.1
  • Powder coat line: 5-stage pre-treatment (zinc phosphate), vertical conveyor, cure oven capacity 200 parts/shift
  • QC: CMM (Brown & Sharpe), weld inspection via VT and magnetic particle testing, coating thickness gauge per batch
  • Certifications: ISO 9001:2015, ISO 14001 environmental — verified on-site

Factory A scored 88/100 on our QCLDM Dolphin audit. Factory B scored 81/100. We recommended Factory A as primary and Factory B as qualified backup.

3. Tooling & Sample Production

Progressive dies for the 7 stamped components were designed and built in 8 weeks at the factory's in-house toolroom (10 CNC machining centers dedicated to tool fabrication). We coordinated:

  • Die tryout with 3D scan comparison against CAD — all 7 components within profile tolerance on first tryout
  • Weld fixture fabrication — 3 fixture sets for the 3 main sub-weldments, validated against the assembly drawing
  • First article: 5 complete chassis assemblies fully inspected by our QC team before shipment

All 5 first-article units passed dimensional inspection, weld visual inspection, and coating adhesion test (cross-cut per ISO 2409, rating 0 — best possible). Customer approved on first submission.

4. Cost Breakdown — Before vs. After

Cost Element China (Before) Vietnam (After) Saving
Factory Unit Price (FOB) $148 $108 −$40
Section 301 Tariff (25%) $37 $0 −$37
Ocean Freight (per unit) $18 $19 +$1
Customs Clearance $15 $14 −$1
Landed Cost / Unit $218 $141 −$77 (42%)

Est. based on 5,500 unit/year volume. Freight rates approximate; vary by load and season.

5. Production & Ongoing Oversight

Production launched on schedule. Our Vietnam team conducts pre-shipment inspection on every container: 100% dimensional check on 10% sample, weld visual inspection per AWS D1.1, coating DFT measurement, and photo documentation of each shipment. Monthly factory visits track production velocity and tooling condition. After 8 months of production, the client has not issued a single quality rejection on this chassis program.

Results Summary

42% landed cost reduction — from $218 to $141/unit
Est. $480K+ annual savings on 5,500-unit annual volume
$275K Section 301 tariffs eliminated — zero tariff on Vietnam origin
Zero quality rejections — 8 months of production
Customer approval on first sample submission
8-week tooling lead time — faster than original China timeline
⏰ Timing matters: This client started their Vietnam qualification 6 months before their next tariff-affected shipping window. Early movers avoid the rush when tariff announcements hit. The factories we work with have limited capacity.

More Case Studies